Woburn Sands and surrounding villages
August 2022 update
On August 2, 2022, Central Bedfordshire Council’s Executive Committee voted to revoke the implementation date of September 2022 for the change of age range of Aspley Guise Village School.
Watch the webcast of the Central Bedfordshire Council Executive Committee meeting where this decision was made.
You can read more about Aspley Guise Village School further down this page.
July 2022 update
With the Aspley Guise, Husborne Crawley, Ridgmont and Woburn lower schools unable to be developed into primary schools for the foreseeable future, additional teaching accommodation will be created at Fulbrook to take children from these schools into Years 5 and 6 . This is from the academic year 2023/24 onwards.
Places have already been allocated to pupils for the coming academic year, 2022/23.
The building works required to expand Fulbrook are currently in the design phase and a planning application will be submitted later this summer.
During the summer holiday:
At Fulbrook, works are already underway on the initial phase of remodelling of existing buildings and this is due for completion by the end of the summer holidays. The sports hall and new teaching block will follow over the next academic year.
At Swallowfield the temporary accommodation for the new year 5 cohort commences in the coming weeks and will be ready for the start of the autumn term. The building works for the permanent accommodation will commence once the temporary accommodation has been completed.
Where we are now
Phase 1
| School | "Have your say" consultation | Statutory consultation, or approval from Regional Schools Commissioner | Design and planning | Implementation of agreed building changes | Two Tier Transition Date |
|---|---|---|---|---|---|
|
Aspley Guise Village School |
Completed |
Completed |
TBC |
TBC |
TBC |
|
Swallowfield Lower |
Completed |
Completed |
Completed |
Not started |
2022 |
|
Fulbrook Middle |
Completed |
Completed |
Completed |
In progress |
2022 |
Planning stage for Woburn Sands and surrounding villages
Below is the latest information on the schools in phase one of Woburn Sands and the Surrounding villages.
Aspley Guise Village School
We’re extremely sorry that we are unable to expand Aspley Guise Village School, which means the school will no longer be able to offer a year 5 place for children in September 2022.
We always knew there would be challenges to overcome at this school, but we were confident we could achieve our plan. Unfortunately, over the last few weeks it has become clear that there were significant reasons why it is no longer possible to continue.
Although the issue of improving highways access to the school has been raised as a potential issue, this needed to be thoroughly explored by our Highways and Planning teams to understand what was possible and the cost of making the access suitable.
It’s as a result of us submitting the formal planning application and the detailed analysis of the issues through this process that led to a conclusion that this issue could not realistically be overcome. We have looked at ways to make this possible but as we do not control all of the access road or the car park, we were unable to make any further meaningful improvements to address the issues. Unfortunately, this has meant that planning consent would likely not be granted for the school expansion.
Until we had fully explored options around planning, increasing the amount of parking and highways matters through the planning application process, we weren’t able to make a definitive decision. It has not been for want of trying, we have explored every option available to us to make this expansion happen but, unfortunately, without planning consent, the project cannot proceed.
What happens next?
An additional Year 5 class is being set up from September 2022 at Fulbrook Academy for children moving from Aspley Guise Village School.
If you would like to speak to one of Central Bedfordshire Council’s Admissions team please email and a phone call can be arranged for you.
Swallowfield Lower School
The process of appointing contractors to undertake the building works is underway.
In April 2022, planning permission was granted by Central Bedfordshire Council’s Development Management Committee for a temporary classroom unit at Swallowfield Lower School, which will support 60 pupils until construction of permanent accommodation is complete, to support the school’s transition to becoming a primary school from September 2022. Watch the Development Management Committee discussion.
Also, so that Swallowfield Lower School can transition to become a primary school in September 2022, planning permission was granted by Central Bedfordshire Council on 16 February, 2022 for the following:
a new teaching block and associated infrastructure
refurbishment of the temporary unit
minor remodelling works to the existing school
additional car parking and cycle/scooter hoops
Fulbrook Middle School
An additional Year 5 class is being set up at Fulbrook for children that had been due to move into Year 5 at Aspley Guise Village School from September 2022.
Planning permission was granted on December 15, 2021, for changes to support Fulbrook Middle School’s transition to become an extended secondary school. Watch the Development Management Committee meeting.
The process of appointing contractors to undertake the building works is underway.
The school is currently a 4 form of entry middle school with an age range of 9 -13 years and will expand its age range to 11-16 years when it becomes a secondary school. The current pupil admission number (PAN) for the school is 110 pupils. This will increase to a PAN of 120 pupils. The number of year groups will also increase from four to five allowing for an overall number on roll of 600 pupils.
The approval of the planning application (CB/21/04325/REG3) will see the following changes:
building a new teaching block and new sports hall
remodelling works to the existing school
car parking
landscaping
associated infrastructure
Central Bedfordshire Council will now undertake work to appoint a contractor and develop a construction schedule. Further updates will be provided on this website when they are available.
Phase 2
| School | "Have your say" consultation | Statutory consultation, or approval from Regional Schools Commissioner | Design and planning | Implementation of agreed building changes | Two Tier Transition Date (Subject to review against growth and agreed model) |
|---|---|---|---|---|---|
|
Husborne Crawley Lower |
Completed |
Completed |
Not started |
Not started |
TBC |
|
Ridgmont |
Completed |
Completed |
Not started |
Not started |
TBC |
|
Woburn Lower |
Completed |
Completed |
Not started |
Not started |
TBC |